DESIGN OF A PROJECT MANAGEMENT SYSTEM AT CV. KHARISMA KARYA NUSANTARA USING THE CRITICAL PATH METHOD (CPM)
DOI:
https://doi.org/10.47701/mzbqqf95Keywords:
Delays, impact, Critical Path Method, Microsoft ProjectAbstract
Project delays have a substantial impact on overall implementation performance; therefore, effective control and scheduling mechanisms are essential to ensure time efficiency throughout every phase of work. CV. Kharisma Karya Nusantara frequently encounters delays caused by excessive overtime and an unstructured reporting system that cannot be evaluated in real time. This study aims to design a project management system and analyze the scheduling impact using the Critical Path Method (CPM). The CPM analysis identified a critical path consisting of preparatory work, lower structure levels 1 to 3, ground floor work, upper structure levels 1 and 2, first, second, and third floor structural works, walls and partitions of the second floor, first floor finishing, and final work. The total project duration calculated using CPM was 588 days. When recalculated using Microsoft Project, the duration was reduced to 337 days, resulting in a time efficiency of 251 days. These findings demonstrate that implementing a well-structured and integrated project management system can significantly enhance scheduling efficiency, minimize delays, and optimize overall resource utilization.
References
Ahmada, M. M., Diansari, B. N., & Buwono, R. I. (2024). Perencanaan Schedule Preventive Maintenance Pada Mesin Web dengan Metode Overall Equipment Efectiveness (OEE) di CV. Indonesia Jaya. Prosiding Sains Nasional dan Teknologi, 14(1), 90-96.
Kusnadi, Subagyo Ade Momon, M. A. N. (2021). PERENCANAAN MANAJEMEN PROYEK DENGAN METODE CPM ( CRITICAL PATH METHOD ) DAN PERT ( PROGRAM EVALUATION AND REVIEW TECHNIQUE ) Pertumbuhan infrastruktur daerah diberbagai sektor terjadi dengan cepat dan terjadi pertumbuhan pada fasilitas infrastruktur Dibut. Jurnal Konstruksia, 13(1), 164–180.
Syahputra, R., Pasaribu, M. F., & Syarif, A. A. (2024). Penerapan Metode CPM (Critical Path Method) Pada Proyek Peningkatan Sarana Dan Prasarana TPS Limbah dan Fasilitasnya Di PT. Putra Kuala Tanjung. IRA Jurnal Teknik Mesin Dan Aplikasinya (IRAJTMA), 3(1), 31–37. https://doi.org/10.56862/irajtma.v3i1.90
Tech, M., Kumar, R. R., Omments, R. E. C., Prajapati, A., Blockchain, T.-A., Ml, A. I., Randive, P. S. N., Chaudhari, S., Barde, S., Devices, E., Mittal, S., Schmidt, M. W. M., Id, S. N. A., PREISER, W. F. E., OSTROFF, E., Choudhary, R., Bit-cell, M., In, S. S., Fullfillment, P., … Fellowship, W. (2021). Penerapan Metode Cpm (Critical Path Method) Pada Proyek Konstruksi Pembangunan Bendungan Lau-Simeme Paket Ii Kab. Deli Serdang. In Frontiers in Neuroscience (Vol. 14, Issue 1). http://fatek.umsu.ac.id
Widyaningsih, D., & Utami, A. W. (2021). Rancang Bangun Sistem Informasi Manajemen Kontraktor pada Perusahaan X Menggunakan CPM. Indonesian Journal of Engineering and Technology (INAJET), 4(1), 25–33. https://doi.org/10.26740/inajet.v4n1.p25-33